Sichuan to become nation's largest hydropower base by 2020

Posting Time:2017-08-03 Browse times:463


      Actively promoting the construction of national clean energy demonstration province


      By 2020 - the installed hydropower capacity will reach 83 million kilowatts, becoming the largest hydropower base in the country

      Build a nationally important natural gas production base with the basic pattern of northeast Sichuan, central Sichuan and west Sichuan.

      August 4, with the world's largest hydropower plant under construction, installed capacity of 16 million kilowatts of the Jinsha River Baihetan Hydropower Station main project started in full, the construction of clean energy base in Sichuan Province to a new level. Baihetan Hydropower Station, together with Wudongde, Xiluodu and Xiangjiaba Hydropower Station, will build an important green energy base in China on the lower reaches of the Jinsha River.

      As China's clean energy resources province and national high-quality clean energy base, Sichuan Province is now actively promoting the construction of national clean energy demonstration province. In the first half of the year, the province's clean energy show "supply and sales" situation.

      From the supply point of view, the Dadu River Shaping two hydroelectric power station, Shuoqu River to go to the school hydroelectric power station and a number of medium-sized hydroelectric power station put into operation, Sichuan Province, the installed hydropower scale exceeded 70 million kilowatts, hydropower-based clean energy accounted for more than 80%, ranking first in the country. During the "13th Five-Year" period, Sichuan Province will adhere to the hydropower-based energy development policy, focusing on the Jinsha River, Yalong River, Dadu River Basin, prioritizing the construction of the leading reservoir power station, and orderly promote the construction of medium-sized hydroelectric power, strictly control the development of small hydropower, scientific and orderly advancement of the province's hydropower development. Focus on the Jinsha River Wudongde, Baihetan, Suwulong, Dadu River, Shuangjiangkou, hard Liangbao, Yalong River, Yangfanggou and a number of large-scale hydropower project construction, accelerate the construction of the "Three Rivers" (Jinsha, Yalong, Dadu River) hydropower base. By 2020, the installed hydropower capacity in Sichuan Province will reach 83 million kilowatts, becoming the country's largest hydropower base. In the first half of the year, natural gas supply in Sichuan Province increased significantly. PetroChina Southwest Oil and Gas Field Company supplied 12.84 billion cubic meters of natural gas to the market, an increase of 18.4% year-on-year, equivalent to replacing 24 million tons of standard coal, reducing emissions by more than 18 million tons.

      From the point of view of sales, the State Grid Power Company of Sichuan Province data show that from January to June this year, Sichuan full-caliber transmission of 43.12 billion kilowatt-hours of electricity, an increase of 1.07% year-on-year. Sichuan hydropower is mainly sent to Shanghai, Jiangsu, Zhejiang, Chongqing and other provinces and cities, the scale of transmission accounted for about 40% of the province's hydropower generation.At the end of June, the "13th Five-Year" period of Sichuan's first hydropower transmission channel - Sichuan-Chongqing Power Grid, the third channel was completed and put into operation. As of 00:00 on August 2, a total of 1.41 billion kilowatt-hours of electricity has been delivered to Chongqing, with a daily average of about 40 million kilowatt-hours, effectively alleviating the pressure on the Chongqing power grid this summer and eliminating the "neck" situation of the Sichuan-Chongqing power grid power exchange.

      In addition to sending hydropower, local consumption is also increasing. Sichuan Province in the first half of the completion of the electricity substitution of 2.647 billion kilowatt-hours, higher than the same period last year. Alternative power is mainly concentrated in coal-fired power plants, metallurgical furnaces, auxiliary electric power, rail transportation, building materials, electric kilns and furnaces, oil and gas pipeline power pressurization and other six areas. The first half of the coal-fired power plant alternative effectiveness, has completed the replacement of 1.508 billion kilowatt-hours of electricity, is expected to consume 3 billion kilowatt-hours of electricity throughout the year.

      Sichuan Province is also actively promoting the construction of natural gas (shale gas) production base, by 2020 will be built in northeast Sichuan, Sichuan, western Sichuan as the basic pattern of the national important natural gas production base. At present, Sichuan Province has launched the Yalong River Basin and Jinsha River downstream wind and water complementary development research and planning, and strive to become the "13th Five-Year" national multi-energy complementary demonstration project.

      Provincial Energy Bureau said, Sichuan attaches great importance to adjusting and optimizing the energy structure, the first in the country to achieve a clean energy-based energy consumption structure, and become a large province of clean energy consumption. "Thirteenth Five-Year" period, Sichuan will strive to achieve "ultra-low emissions", renewable energy and fossil energy clean use to meet the new energy demand, the basic formation of hydropower and natural gas as the main body of new energy and fossil energy clean use as a complementary multi-energy Complementary pattern.